On the exterior, we’ve completed the sidewalks, courtyard, fire pit, and the courtyard coating. Landscaping and grassing are now finished, so the outside of the building is nearly complete and really coming together beautifully.
Inside the building, we’ve reached several major milestones:
Inside the building, we’ve reached several major milestones:
- Final coats of paint are in place
- Millwork and countertops are installed
- Ceiling trim and lighting are nearly complete
- Flooring is down in most areas
- Mechanical equipment is installed
One of the most exciting updates – the bowling alley is installed!
The pool builder is back on site completing the final preparation work, with plaster scheduled for next week. Pool equipment is currently being installed, and once plaster is complete, the pool will be filled in the coming weeks.