What an incredible day! On Friday, November 7, 2025, Moose members from across the fraternity came together to celebrate the Ribbon Cutting Ceremony for the AAA Project. The event was filled with excitement and pride as we welcomed distinguished guests, including Scott Hart, CEO, John Reiter, Chairman of the Moose International Board, the Moosehaven Board, Moose International Board, honored dignitaries, Moosehaven residents and staff, and the talented Scherer Construction team who helped bring this vision to life.We are thrilled to be nearing the finish line! Our heartfelt thanks go out to every member of this amazing fraternity for your generosity and unwavering support. Because of you, we now have a stunning new Pavilion and a state-of-the-art Sports & Recreation Center—a true testament to what we can achieve together!
Moosehaven AAA Recreation Center – November 2025 Construction Update
November has been a highly productive month on the project, with major progress made across the sitework, building exterior, and interior finishes as we move into the final phases of construction.
Sitework & Exterior Progress
- Significant progress was made on sidewalks, courtyard concrete, and paving on the east and west sides of the building. Cart-path parking and driveway paving are underway and will wrap up in early December.
- Pond grading and sodding are now complete.
- Exterior siding installation is complete, and the building is approximately 90% painted on the exterior.
- Roof gutter and downspout installation began this month and will continue into early December.
Pool Building & Pool Area
- The Extrutech ceiling installation over the indoor pool is complete.
- Stucco finishes throughout the pool area were completed this month.
- Epoxy primer and paint on the pool soffits, beams, and walls will begin immediately after Thanksgiving, followed by scaffold deck removal and epoxy flooring in early December.
Interior Building Progress
- Interior painting of walls, soffits, and exposed structure reached substantial completion.
- Acoustical ceiling grid installation was completed, allowing overhead trim and fixture installations to progress.
- Lighting, ceiling fans, electrical trim, mechanical trim, and fire alarm device rough-in are all underway and advancing steadily.
- HVAC equipment and exterior condensers were installed and connected. The system is now being prepared for official startup during the first week of December.
Looking Ahead – December Work
According to the four-week schedule, several major milestones are planned for early December:
- Final interior paint
- Fire sprinkler trim and low-voltage trim
- Door and hardware installation
- Pool restroom finishes
- HVAC startup and mechanical final inspections
- Start of LVT flooring, sports flooring, and bowling alley installation
- Continued landscaping, irrigation, and tree installation to finish out the exterior